We’re happy to answer your questions!
LOOPED brings together new ideas for the collaborative, digital and phased planning and implementation of infrastructure. This naturally raises questions – you can find the answers to the most frequently asked ones here.
Thank you for your interest in the information sessions! If you missed them or would simply like to watch them again, you can find the presentation slides with explanations HERE.
01
To what extent are engineering firms needed?
For the LOOPED project, we are primarily seeking transport engineering firms with whom we can investigate the impact of a serial production train on improving accessibility at bus stops. In addition, we are seeking services in detailed design and construction supervision, to be provided in close coordination with LSBG and the contractors carrying out the works. It is correct that the LSBG wishes to provide – or has already provided – its own planning services for the structural design, based on a GIS-based needs analysis and a BIM model of a standard bus stop, as preparatory work for our project partners. A final description and clarification of the scope of internal and external services is still pending.
02
How will on-site construction supervision be organised?
Our colleagues in the Urban Roads Division (GB S) will be responsible for local construction supervision (BÜ). As GB S generally outsources BÜ, this should also apply to the LOOPED project. However, final agreements between the LOOPED project team and GB S are still pending.
03
What would happen if the BIM sample bus stop had to be adapted to the actual locations?
To pave the way for serial construction, our detailed needs analysis is designed to ensure, at an early stage, that only those bus stops which correspond to similar construction requirements and whose BIM model can blend seamlessly into the surroundings are grouped into demand clusters and batches (a serial sequence of 6 bus stops). The question of how to address unavoidable deviations in the planning stage is to be incorporated as a use case into the agent-based construction process simulation, which we are already developing in collaboration with a start-up. In principle, the proportion of serial construction within the construction process should be increased to the extent that it yields advantages over conventional individual project planning. Unavoidable site-specific adjustments should therefore, where possible, be carried out either beforehand or afterwards to ensure the reliability and cost-effectiveness of the series. Once the requirements analysis has been completed, we will be better able to describe the scope and implications of site-specific constraints in order to develop targeted solutions for the specified use case.
04
Have planning processes in Hamburg involving public authorities (TöB) already been integrated?
The associations’ expectations have already been taken into account in the prioritisation of demand clusters and bus stops. Potential construction windows have already been broadly aligned with the construction plans of the relevant district-level authorities for the years 2027/28. The BIM model bus stop is based, according to different implementation variants, on the guidelines of the Hamburg Transport Association. The models already include all possible categories of utility routes that we might encounter in the existing infrastructure. The business processes for joint procurement across all participating implementing bodies (in this case, for example, LSBG in conjunction with Hamburg Energie) have already been agreed upon through the Cooperative Procurement scheme. However, the ‘Serial Construction’ methodology has not yet reached the necessary level of maturity for the effective operational integration of these processes; this is the subject of further product development. To secure the synergies and economies of scale offered by Serial Construction in the LOOPED pilot project, we are deliberately omitting the construction of new stops in order to minimise potential interfaces with public works projects at an early stage. The preliminary needs analysis aimed at grouping similar stops together is also intended to help us proactively remove stops with potentially critical points of contact with utility lines from the proposed clusters of demand, in order to pave the way for the ‘barrier-free’ Serial Production Train. The preceding analysis also takes into account unavoidable adaptations to local conditions.
05
What exactly do you mean by the question of what volume would make it worthwhile for you to get involved in the project?
In fact, this question relates primarily to the partner profiles of construction companies and precast manufacturers, rather than to engineering firms. This is an extremely crucial issue for us, as it enables us to offer you the prospect of an attractive project volume even during the pilot phase and to draw corresponding conclusions regarding the scope, duration and complexity of the tendering process. By providing a robust assessment, you will help to ensure that our project requirements are aligned with your expectations at an early stage and in a reliable manner.
06
How should any amendments to the contract be handled as the project progresses?
Subject to the progress of our procurement and contract framework (VV framework), regressive amendment management is to be overcome through collaborative price updates using the open-book method, analogous to elements of ‘Integrated Project Management’ (IPA). Our outlined approach to the VV Concept currently envisages moving into the next iteration/cycle using fixed, performance-based unit prices to call off a fixed number of batches (small series of 6 bus stops each) from the framework contract, in order to pause after completion of each batch in line with Lean Construction Management (LCM) and discuss any necessary adjustments or updating the agreed unit prices for use in the new batch. The extent to which potential cost caps or incentive mechanisms might play a role here, subject to the restrictions of budgetary and corporate law, has not yet been conclusively defined under public procurement and contract law. We would ask for your patience in this regard.
07
What data formats are used in the methods employed (e.g. BIM/AVA)?
We make use of non-proprietary and therefore open data formats. Whilst data exchange within the BIM (Building Information Modelling) methodology will take place via the IFC (Industry Foundation Classes) data format, the AVA (Tendering, Award and Settlement) methodology will utilise the conventional data types in the GAEB data format. The software solutions to be used by the project partners must be capable of processing these open data formats. Commercially available products such as Revit (Autodesk) and Orca are generally capable of doing so. Proprietary data formats should only be used if there are no open alternatives and the LSBG offers, amongst other things, licences, training and support services; this is the case, for example, with the solutions provided by the start-ups already involved in the project.
08
Who is the point of contact for enquiries regarding the technical requirements of BIM models?
Should you have any questions regarding the technical requirements of our design variants for the BIM model bus stop, please feel free to contact the LSBG LOOPED project team directly via the designated Funktionspostfach. Please accept our apologies that, for procedural reasons, we may not be able to address specific enquiries relating to the translation of given requirements into practical application in the areas of planning, factory production and delivery, and construction. However, we would be happy to refer you to the publicly available catalogues of the ReStra (Hamburg regulations for the planning and design of urban roads) and the HVV-Leitfaden on the accessible development of bus stops. The design variants of our BIM model bus stop comply with the technical requirements of both sets of regulations.
09
Will the tendering process be based on the Integrated Project Management (IPA) approach?
Subject to the progress of our procurement and contract framework (VV framework), elements of the rail and waterway partnership model are to be incorporated into the VV framework. The partnership models also incorporate elements of the IPA concept and are currently undergoing a trial phase at Deutsche Bahn AG (DB) and the Waterways and Shipping Authority (WSA). In contrast to the fixed structure of an IPA, we plan to design our VV Concept to be as modular as possible, in order to keep procurement processes flexible whilst remaining true to the methodology. Ultimately, we aim to strengthen and promote the LOOPED Product Vision for applying the ‘Serial Construction Methodology’ to other categories of structures and implementing bodies. Subject to further developments, you can find initial information on the proposed VV concept HIER
Municipal infrastructure construction – Start fresh with LOOPED?
Whether you are a municipal authority, a specialist planner or an industry partner – LOOPED stands for innovation through new ways of working together. Please feel free to get in touch!
Interested in LOOPED?
Please feel free to contact us!